September 2008


Click to enlarge




The eight and last sluice gate
was put in place
during August 2008.


June 2008



Two on four of the pillars (number 3 and number 4) have been conmpleted. the two others are currently being iron structured and will soon be concreted.

The sluice gates have already been made in factories. They are taken on the site during the month of June and will be put in place by the end of the summer.



Click to enlarge
This piece called "chair" will be inserted into the pillar to avoid too much efforts on it during the sluice gates installation (Picture : Syndicat Mixte)


Click to enlarge
The iron structure of the pillar being made (Picture : Syndicat Mixte)


Click to enlarge
The pilar concreted. To be completed some more equipments needed for the sluice gated functioning will be added (Picture : Syndicat Mixte)


May 2008



Works progressing on the east side

Currently, the iron structure of the dam's plinth is made. The next step will be the concreting. It is already possible to guess the shape of the future sluice gates that will be put in place there.



Click to enlarge


Click to enlarge


Click to enlarge


Click to enlarge

Water through the first half of the new dam

Before the whole dam is completed, the sluice gates already put in place have the same fonction as the old ones : they are closed during high tide so that the floot can't get into the river.



Click to enlarge


Click to enlarge


Click to enlarge


March 2008



Click to enlarge
The first half of the dam is completed, now water can go through it, even if it doesn't work yet as it will when the whole dam is finished. (Crédit Syndicat Mixte).


Click to enlarge
To build the second half of the dam, it is necessary to create a watertight structure on the other side of the Couesnon.again (Crédit Syndicat Mixte).


Click to enlarge
At the beginning of March, the watertight structure is made. (Crédit : Syndicat Mixte).


December 2007



Click to enlarge
Five piles and four sluice gates are now completed. (crédit: Syndicat Mixte)


Click to enlarge
One special sluice, dedicated to fishes, has been constructed on the side of the dam. (crédit: Syndicat Mixte)


Click to enlarge
A "maritime" balcony will be there, made of wood. first, the structure had to be done. (Crédit : Syndicat Mixte)


October 2007

THE FIRST HALF OF THE DAM NEARLY COMPLETED

The first four sluice gates are put in place.

Now the supersructures are on : a bridge on the top of the dam has been made of concrete so that visitors can cross the river (september 2007).




Click to enlarge
the fourth sluice gate has been put in place by early octobre. Crédit: Syndicat Mixte

Click to enlarge
the bridge made of concrete, on top of the dam. Crédit: Syndicat Mixte


Click to enlarge

Ensuite, les premières opérations relatives aux superstructures du barrage ont débuté : Les éléments composant la charpente métallique du balcon maritime ont été posés. 

Le balcon est porté par des consoles métalliques, ancrées sur les piles.


Click to enlarge

The inside of this house will be changed to become the Technical Office of the futur dam.

August 2007

THE FIRST SLUICE GATE ON SITE

The civil engineering is now completed (concrete, piles...). The new step, related to the equipments of the sluice gates is now starting. 

The sluice gates are made in two pieces, the arm and the apron) by two different factories (on next to Nantes, the other next to Caen) and are assembled on site.
The first of the eight sluice gates has arrived on the works area by the end of august.





Click to enlarge
Vue sur les 5 piles du demi-barrage Crédit: Daniel Fondimare


Click to enlarge
Chaque vanne fait 9 m sur 7m40, d'où la nécessité d'un transport en convoi exceptionnel Crédit: Daniel Fondimare


Click to enlarge
Pose de la première vanne entre deux piles crédit: Syndicat Mixte (Denis Bellenger)

JULY 2007

News of the dam

Next to the civil engineering, the first equipements that are related to the future sluice gates are put on site.




Click to enlarge
The first three piles. Crédit: Syndicat Mixte

Click to enlarge
the forth pile. Crédit: Syndicat Mixte

Click to enlarge
A sluice gate's axis. Crédit: Syndicat Mixte

JUNE 2007

The concrete works are completed for the bottom of the fisrt half of the dam. The piles are made.




Click to enlarge
The shaope of the concrete reproduices the shape of the future sluice gates - crédit : Syndicat Mixte


Click to enlarge
The second pile finished- crédit : Syndicat Mixte


Click to enlarge
the side of the dam is nearly finished - crédit : Syndicat Mixte


MAY 2007



Click to enlarge
Crédit : Syndicat Mixte


Click to enlarge
Head of one pile - Crédit : Syndicat Mixte


Click to enlarge
Concrete cast lasts one day only - Crédit : Syndicat Mixte


APRIL 2007

The works are now on. The beginning first half of the dam can now be seen.
three of the piles are can now be guessed, as they are under iron building. The concrete casts are about to be made.



Click to enlarge
The concrete steps are due to be finished by the end of may - Crédit: Syndicat Mixte


Click to enlarge
The concrete cast will be made in may - Crédit: Syndicat Mixte


Click to enlarge
The side of the dam, on the edge of the river is realised - Crédit Mixte: Syndicat Mixte


FEBRUARY 2007


THE FIRST CONCRETES

Now that the works area has been cleared from water, the first concretes can be done.



Click to enlarge
Fin de la mise à sec du batardeau avant la réalisation des fondations - Crédit: Syndicat Mixte


Click to enlarge
Démarrage des travaux de fondations du futur barrage (battage de rideaux de parafouilles) - Crédit: Syndicat Mixte


Click to enlarge
Réalisation des premiers gros béton mi-février - Crédit: BRL


November 2006


The works



Click to enlarge
A bridge is built against the existing dam. Vehicles will use it to create the dry area / october 2006 - Picture BRL Ingénierie


Click to enlarge
The brifge from the side of the river / november 2006 - Picture: Syndicat Mixte


Click to enlarge
Beginning of the digging of the river's bed to prepare the future dry area / october 2006 - Crédit : BRL Ingénierie


October 2006


Works on the existing dam and creation of a new final part for the rain water evacuation

Works on the existing dam are made :
- a dam is created on top of it so that the vehicles can safely drive on it,
- new ways (pertuis) are opened into the dam to let the water going upstream escape.

Morover, the final part for the evacuation of rain water is completed.



Click to enlarge
The bridge over the dam - Picture : Syndicat Mixte


Click to enlarge
The pertuis - Picture : Quille


Click to enlarge
The evacuation part for rain water - Picture : Syndicat Mixte



Click to enlarge
The area of the works in september - Picture : Syndicat Mixte


Click to enlarge
Rain water works - Picture : Syndicat Mixte


September 2006


WORKS AREA SETTLED, THE WORKS CAN START

The work area has started to be developped on the 7th of june 2006 by the companies Quille and Mastellotto.

Drilling have also been made in the Couesnon bed where the future new dam foundations will be built.



Click to enlarge
Zone de vie du chantier - Photo : Syndicat Mixte


Click to enlarge
Sondages dans le lit du Couesnon - Photo : Quille


Click to enlarge
Piste d'accès des engins - Photo : Syndicat Mixte


June 2006


Starting of the building work of the new dam on Couesnon


The first heavy vehicles are awaited for this beginning of June 2006.



May 2006


Public meeting on the launching of the works of the new dam on Couesnon

On Thursday May 4,2006 a meeting of presentation of the conditions of achievement of the new dam on Couesnon was held in the room Alain Cuny de Beauvoir and chaired by Philippe DURON, president of the Joint Council Bay of the Mont-Saint-Michel and president of the regional Council of Lower Normandy.

This meeting made it possible to inform the residents of the building site on the zones concerned with its installation, the schedules of work, the plan of transport ...